Tub-to-Shower Conversion in Westwood Lakes, FL: What It Takes
A tub-to-shower conversion in Westwood Lakes, FL typically runs $3,500 to $10,000 and takes five to ten working days once materials are on site. The job means removing the existing tub, rebuilding the wet area with proper waterproofing, and setting a shower pan, tile, and fixtures that fit the same footprint. Most Westwood Lakes conversions stay in that price range because they reuse the existing drain location. Call (844) 761-9356 for a free on-site estimate before you commit to anything.
How a Tub-to-Shower Conversion Actually Runs, Stage by Stage
Most contractors describe this job as “we handle everything.” That tells you nothing. Here’s the real sequence, with the days and decisions attached.
Stage 1: Measure and confirm the footprint (day 1, about an hour)
We pull the tub dimensions, check the drain location, and confirm whether the valve is a single-handle or three-handle setup. You decide right here whether we stay in the exact tub footprint (lowest cost, fastest) or widen the shower by a few inches into an adjacent wall. Widening means moving the valve and drain, which adds plumbing and usually a permit revision.
Stage 2: Demo and rough-in inspection (days 1 through 3)
The tub comes out, along with the old surround and any rotted backer. On a 1960s CBS home, we open the wall to check the drain and valve. If the valve is original, this is the moment to replace it. We don’t want to cut into a new shower wall two years from now. The rough plumbing and any framing get inspected before anything closes back up.
Stage 3: Waterproofing and pan (days 3 and 4)
This is the stage that decides whether the shower lasts. We set a sloped mortar bed or a pre-formed pan, then a bonded waterproofing membrane over the walls. A flood test confirms the pan holds before tile goes down. Skipping or rushing this step is the most common reason showers fail in South Florida’s humidity.
Stage 4: Tile, glass, and trim (days 5 through 8)
Wall tile, grout, a shower niche if you want one, and the glass enclosure. You’ll choose tile size and layout before this stage starts. Large-format tile means fewer grout lines and a cleaner look, but it requires a flatter substrate and cuts differently around the drain. Glass gets templated after tile, so there’s a short wait on fabrication.
Stage 5: Final inspection and walkthrough (days 9 and 10)
We test the drain, check the valve for leaks, seal the grout, and walk the finished shower with you. Any punch-list items get noted and handled. You get the permit close-out documentation for your records. That’s the sequence. Most of the duration is drying time and glass fabrication, not labor.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices You’ll Make: Materials and Layout
Almost every decision on this job comes down to trade-offs between cost, maintenance, and how the shower will look in ten years. Here’s what actually gets picked between.
- Shower pan: pre-formed acrylic vs. tiled mortar bed. A pre-formed acrylic pan is faster to install and less expensive, but it can feel hollow and shows scratches over time. A tiled mortar bed with a linear or center drain matches the walls and holds up better, at higher cost and a few extra days.
- Wall tile: ceramic, porcelain, or large-format porcelain. Ceramic is the budget pick and works fine in a guest bath. Porcelain resists moisture better. Large-format porcelain (24×48 or bigger) looks the most modern and cleans easiest, but the substrate has to be dead flat.
- Waterproofing: cement board with a liquid membrane vs. a bonded sheet membrane. Cement board alone isn’t waterproofing. A liquid-applied membrane is common and reliable when applied to the right thickness. A bonded sheet membrane is more consistent in humid conditions.
- Glass: framed vs. frameless, clear vs. low-iron. Frameless clear glass is the cleanest look. Low-iron glass removes the slight green tint of standard glass. Framed enclosures cost less and hide minor wall imperfections.
- Fixtures: valve and trim. A pressure-balance valve is the standard. A thermostatic valve holds temperature better but costs noticeably more and needs a different rough-in. Kohler trims are a common choice in this price bracket.
- Niche and bench. A recessed niche is cheap to add during the build. A built-in bench adds framing and tile and usually requires a larger footprint.
What Tub-to-Shower Conversion Costs in Westwood Lakes, FL
Expect $3,500 to $10,000 for a tub-to-shower conversion in Westwood Lakes. The same footprint at the low end, a larger shower with frameless glass and tiled pan at the high end. Five variables push the number up or down:
- Footprint changes. Staying in the exact tub outline keeps it low. Widening into a wall or closet means framing, plumbing relocation, and a permit revision.
- Existing condition behind the tub. Rotted backer, old cast-iron drains, or a corroded valve add demo and rough-in cost.
- Material grade. Ceramic and a framed enclosure at the bottom; porcelain, a bonded membrane, and frameless glass at the top.
- Permit scope. A like-for-like swap with the same drain location is a smaller permit than one that moves plumbing.
- Glass and fixtures. Templated frameless glass and thermostatic valves are the two biggest line-item jumps.
A written estimate lists the pan, membrane, tile, valve, drain, glass, and permit line by line. It should say what’s included: demo, haul-away, waterproofing, and final inspection. What it typically doesn’t include: structural repairs found mid-demo, or moving a wall that wasn’t in the original scope. We note those in writing before work starts so the number doesn’t move. If the shower is part of a wider project, that belongs with our Bathroom Remodeling service.
See the difference
Before
After
Before
After
Before
AfterWhat Westwood Lakes Homes Do to This Job
Westwood Lakes is a built-out, post-war suburb, ZIP 33165. Nearly every project here is a renovation on a 1950s to 1970s CBS lot, not new construction. That shapes this job directly. Miami-Dade County’s 40-year recertification and post-Surfside inspection rules apply to aging concrete-block homes, so any work that touches structure or plumbing gets looked at against current code. The flood-zone elevation rules on this low-lying land west of the urban core can affect how a shower pan and drain are set, especially on a raised slab.
Inside these homes, the original tubs often sit over cast-iron or old galvanized drains, and the wall behind them was never properly waterproofed by today’s standards. After the summer downpours, we routinely find water intrusion at the roof-wall junctions and around the jalousie window frames, which on a bathroom job can mean the wall behind the shower is wet long before you notice. That’s why the drain inspection on day 1 isn’t optional here. The subtropical climate, with hurricane season from June through November, also means we spec mold-resistant backer and a bonded membrane by default, not as an upgrade. If you’re tackling the roof at the same time, homeowners often pair this with Metal Roofing in Westwood Lakes or Tile Roofing in Westwood Lakes. Our Westwood Lakes service page covers the full area.
Serving Westwood Lakes, FL – Our Local Coverage Area
We serve Westwood Lakes and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked: Tub-to-Shower Conversion in Westwood Lakes
Most Tub-to-Shower Conversion jobs in Westwood Lakes take five to ten working days once materials arrive. The first two to three days are demo and rough-in, the next two are waterproofing and pan work, and the last few are tile, grout, and glass. Glass fabrication adds a short wait because it’s templated after the tile. Call (844) 761-9356 for a firm timeline after we see the space.
Yes, a permit is typically required in Miami-Dade County when plumbing or the shower pan is altered. A like-for-like swap may qualify for a smaller permit, but moving a drain or valve always does. We pull the permit and schedule the inspection so you’re covered. Call (844) 761-9356 to confirm your scope and permit needs.
Often, yes. If the new shower stays in the exact tub footprint and the drain location matches, the plumbing can stay put. That’s the lowest-cost version and the fastest to complete. Widening the shower into a wall or closet means moving the valve and drain, which raises the price and adds a permit revision. Call us to evaluate your layout.
Expect $3,500 to $10,000 for a tub-to-shower conversion in Westwood Lakes. The low end covers the same footprint with ceramic tile and a framed enclosure. The high end covers a larger shower, tiled pan, bonded membrane, and frameless glass. Call (844) 761-9356 for a written line-item quote; estimates are free.
Every Tub-to-Shower Conversion we do is covered by the 730-Day Done Right Promise. If the workmanship fails, we make it right. That’s one of the longest workmanship guarantees in the residential construction space. Ask about it on the call so you know exactly what’s covered.
Get a Free Estimate for Your Westwood Lakes Conversion
We’ll come out, measure the tub footprint, check the drain and valve, and give you a written line-item estimate with the permit scope spelled out. No-pressure, no guesswork on the number. You’ll leave the visit knowing your realistic price range and timeline. Call (844) 761-9356 to schedule your free estimate for Tub-to-Shower Conversion in Westwood Lakes.