Garage Conversion ADU in Tamiami, FL: What It Takes and What It Costs
A garage conversion ADU in Tamiami typically costs between $53,100 and $153,400 and takes 3 to 5 months from permit drawings to final inspection. The job converts an attached garage into a legal, rentable living unit with its own kitchen, bathroom, sleeping area, and separate entrance, and because Miami-Dade requires full permit and wind-load compliance on the change, most of the timeline lives in review and inspections, not construction. Call (844) 761-9356 for a free on-site estimate.
How We Build a Garage Conversion ADU, Stage by Stage
Most contractors describe a conversion as if the hard part is the framing. In Tamiami, it isn’t. Here’s the actual sequence we run, with the decisions you’ll own at each stage.
Stage 1: Site assessment and permit drawings (2 to 4 weeks)
Day one is not demolition. It’s a walkthrough that documents what’s already there, including any prior owner’s work that was never permitted. We measure the slab, check ceiling height and the existing footings, and confirm the garage door opening can be closed in as a wall with a window or a glass door under Miami-Dade’s High Velocity Hurricane Zone rules. You decide the unit’s layout and where the kitchen and bath sit, since that choice drives everything downstream. Drawings go to Miami-Dade product approval (NOA) review here, which is often the longest wait on the whole job.
Stage 2: Demolition and slab prep (3 to 5 days)
Out comes the old garage door, the opener and track, and any drywall or paneling. We grind and level the slab, which on a 1970s-80s block home is usually close to floor-grade already. This is also when we open the floor in one spot to confirm the drain runs before plumbing gets committed. If your garage holds a water heater or laundry, we relcoate those now, and that’s a decision you’ll want to make in stage one, not here.
Stage 3: Rough-in and framing (2 to 3 weeks)
Framing for the closing wall, the bath walls, and any door or window openings. Then plumbing, electrical, and HVAC rough-in, followed by the first inspection. Because Tamiami is in the hurricane zone, every opening and fastener gets called out on the drawings before framing starts, so the inspector isn’t asking for changes mid-build.
Stage 4: Insulation, drywall, and finish (4 to 6 weeks)
Insulation and drywall go in, then flooring, cabinetry, counters, tile, fixtures, and paint. You’ll pick most materials during this stage or just before it, and this is where the budget moves if you upgrade. Cabinet and countertop selections are a good example of where homeowners often pair this with Cabinets & Countertops in Tamiami to keep the kitchen package consistent.
Stage 5: Final inspections and handover (2 to 3 weeks)
Final electrical, plumbing, and building inspections, then the certificate of occupancy that makes the unit legal. We walk the finished space with you, hand over the permit closeout, and start the workmanship warranty. The whole package is covered under our 730-Day Done Right Promise.
If the garage conversion is part of a larger plan that includes a new structure or a bigger footprint, the wider scope lives on our Home Additions & ADU in Tamiami page.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices You’ll Make Between a Basic and a Premium Conversion
- Closing the garage opening: framing a solid wall with a window is the budget-friendly route and gives better wall insulation. A glass slider or French door keeps light and sightlines from the house but costs more and has to meet impact rating. Both are approved approaches in Tamiami.
- Floors: luxury vinyl plank is the practical default for a rental unit and holds up well in humidity. Porcelain tile is a step up, feels cooler in Florida summers, and costs more installed. Carpet in a humid climate is a mistake.
- Kitchenette vs full kitchen: a full range and refrigerator cost more in both materials and electrical. A two-burner cooktop and an under-counter fridge is enough for many rentals and shaves from the budget.
- Bathroom configuration: a walk-in shower with tile is easier to maintain and simpler to permit than a tub, and on a concrete slab a tub drain needs a deeper cut. We default to shower unless you want the tub.
- Exterior cladding on the new wall: James Hardie fiber cement holds paint in Florida sun far better than wood or vinyl, and on a conversion like this we use it on the closing wall as standard for that reason.
- Cooling: extending the existing system with a minisplit is usually the cleanest route; a small dedicated mini-split gives the renter control but costs slightly more upfront.
What a Garage Conversion ADU Costs in Tamiami, FL
Plan on $53,100 to $153,400 for a garage conversion ADU in Tamiami. The low end reflects a stripped-down conversion with a kitchenette, a compact shower bath, vinyl flooring, and simple finishes. The high end reflects a full kitchen, premium tile and cabinetry, a larger footprint with a relocated water heater and laundry, impact windows throughout, and upgrades that push into a finished, rentable, market-rate unit. The variables that move the number:
- Existing condition. An unpermitted Florida room or prior enclosure that needs legitimizing or demolishing can add weeks and real cost before the conversion even begins.
- Plumbing and electrical relocation. Moving the water heater, laundry, or a main panel costs more than leaving them in place, and it’s the most common surprise in the quote.
- Opening and glazing. Impact-rated windows and doors cost more than standard, and on a conversion they’re mandatory, not optional.
- Kitchen and bathroom grade. The fixtures and finishes in these two rooms account for a wide swing in the number.
- Permit scope. A clean, well-drawn permit package gets through Miami-Dade review faster; a package that needs revisions costs time and review fees.
Our written estimate is line-item and fixed. The number you see is the number you pay. It includes permit drawings, the permit itself, construction, and inspections. It does not include furniture, appliances you source separately, or landscaping around the new entry, which we flag upfront so nothing is a surprise. Calls get answered by a live person at (844) 761-9356.
See the difference
Before
After
Before
After
Before
AfterWhat Tamiami Homes Specifically Do to This Job
Tamiami (ZIP 33184) is unincorporated Miami-Dade, and the housing stock here is almost entirely 1970s-90s single-family concrete-block ranch homes, with low-rise Mediterranean townhome clusters along the SW 8th Street corridor. That build era matters: many garages were built with a single-entry slab and no separate electrical meter, so we plan metering early. The bigger issue is that plenty of these homes carry unpermitted Florida rooms, patio enclosures, or carport conversions from prior owners, and a contractor pulling a permit here routinely has to legitimize or demolish past work before the new ADU scope can pass Miami-Dade inspection. The other constant is the High Velocity Hurricane Zone code: every opening needs a product approval (NOA) and post-Andrew wind-load compliance, so permit drawings and inspection sequencing drive the schedule, not design trends. Add near-daily summer thunderstorms and salt-laden air, and exterior scheduling and water-intrusion detailing get planned around the weather, not the other way around.
Serving Tamiami, FL – Our Local Coverage Area
We serve Tamiami and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – Garage Conversion ADU in Tamiami
Plan on 3 to 5 months from signed drawings to certificate of occupancy. Permit review and the final inspection sequence typically account for a third or more of that time, while the physical build runs 8 to 12 weeks. Call (844) 761-9356 to get a timeline specific to your garage.
Yes. Any conversion that adds a kitchen, bathroom, or sleeping area requires a building permit, and because Tamiami sits in Miami-Dade’s High Velocity Hurricane Zone, every new opening and fastener has to meet wind-load and product-approval requirements. We pull the permits and manage the inspection sequence. Call (844) 761-9356 for a free estimate.
Usually yes, if the bathroom is placed near an existing drain and the water heater stays put. Moving a main panel or relocating a water heater adds cost and time. We map these constraints on day one so the layout works around them. Call (844) 761-9356 to walk through your garage.
The range is $53,100 to $153,400 depending on finishes, kitchen scope, existing condition, and how much gets relocated. Our written estimate is line-item and fixed, with 0% financing for 18 months and $1,000 off projects over $10,000 available. Call (844) 761-9356 for an exact quote.
Every conversion is covered by the 730-Day Done Right Promise, and if it’s not done right, we make it right. The permit closeout and inspection record come with the unit at handover. Call (844) 761-9356 with questions about coverage.
Get a Free Garage Conversion ADU Estimate in Tamiami
Call (844) 761-9356 and we’ll schedule a free on-site estimate for your garage conversion ADU in Tamiami. A live person answers every call, day or night. On the visit we measure the garage, note any prior unpermitted work, talk through layout and finishes, and leave you with a line-item quote and a realistic timeline. If you’re also thinking about a new detached structure, explore our Home Additions & ADU service, and see the neighborhoods we cover on our Tamiami page. Pair the unit with Backsplash, Tile & Flooring in Tamiami to finish the floors and kitchen wall to match.