Garage Conversion ADU in Kendall, FL: What It Takes and What It Costs
A Garage Conversion ADU in Kendall typically runs $45,000 to $130,000 and takes 3 to 5 months from permit submittal to final inspection. The job means turning an attached garage into a permitted, separately livable unit: new slab and moisture barrier, framing and insulation, mechanical, electrical and plumbing rough-in, finishes, and a Miami-Dade County certificate of occupancy at the end. Call (844) 761-9356 to schedule a free on-site estimate and get a written line-item scope before you commit to anything.
How a Garage Conversion ADU Comes Together, Stage by Stage
Most contractors describe this job as “we handle everything.” That tells you nothing. Here’s what actually happens, in order, and what you’ll be deciding along the way.
Stage 1: Feasibility and drawings (weeks 1 to 4)
We measure the garage, check ceiling height and the existing slab, and look at how the unit will tie into the house’s electrical panel and plumbing. You decide the layout: studio versus one-bedroom, where the kitchenette sits, whether the entry comes from the house or a new exterior door. A designer or draftsperson turns that into permit drawings. This is the stage where a bad assumption is cheapest to fix.
Stage 2: Permits through Miami-Dade County (weeks 3 to 8, overlapping)
Submittal, plan review, and any comment rounds. Garage conversions in unincorporated Miami-Dade move through county review, not city review, and the county wants product approvals on file for anything in the building envelope. You’ll decide whether the unit gets its own utility meter or sub-meters off the house. We pull the permit and keep the inspection log.
Stage 3: Demo and rough-in (weeks 2 to 4 of construction)
The garage door comes out and gets framed and finished as a wall. That’s the moment most Kendall homeowners don’t expect: the front of the house changes character, so you’re choosing between stucco to match and a James Hardie panel accent. Then slab prep and moisture barrier, framing for the new bath and kitchenette, and electrical, plumbing, and HVAC rough-in. Rough inspections happen before anything gets closed up.
Stage 4: Insulation, drywall, and systems (weeks 3 to 5)
Spray foam or batt insulation in the walls and ceiling, drywall, then the mechanical trim. A converted garage runs hotter than the rest of the house because it was never conditioned and often sits under low attic space, so we size a dedicated mini-split or extend the existing system with a properly calculated load. You pick the finish level here: paint, flooring, cabinet package.
Stage 5: Finishes and final inspection (weeks 4 to 6)
Flooring, kitchenette cabinets, bath fixtures, doors, trim, and paint. Then the final inspections and the certificate of occupancy. Most jobs finish in the 3-to-5-month window, with the back half of that schedule driven by inspection availability more than by labor.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices That Actually Shape Your Kendall Garage Conversion ADU
Every one of these is a real fork in the road, and the honest trade-off matters more than the brochure.
- Slab and moisture control: a garage slab typically sits lower than the house floor and has no vapor barrier. Building up a treated subfloor with a barrier costs more upfront but keeps the unit from feeling damp through Miami’s wet season. Skipping it is the single most common shortcut we correct.
- Wall assembly and exterior finish: stucco to match the existing CBS house reads as original and holds up in the salt air, while a fiber-cement panel like James Hardie gives a cleaner modern line on the former garage face. Both are hurricane-zone compliant when installed to the county’s product approvals.
- HVAC: a dedicated ductless mini-split is simpler and lets the tenant control their own comfort; extending the house system is cheaper to install but can overload a unit that was sized for the original footprint.
- Kitchenette package: a compact run with a sink, two-burner cooktop, and under-counter fridge versus a fuller galley. A semi-custom line like Wellborn or KraftMaid gives you door styles and finishes that hold up; stock boxes save money but limit the layout in a narrow garage footprint.
- Bathroom configuration: a curbless walk-in shower reads larger in a tight unit and is easier to clean; a tub-shower combo suits renters with kids. The plumbing location drives this more than preference does.
- Windows and doors: impact-rated glazing is the norm here, not an upgrade, and it’s what the county wants to see in the product approvals.
What a Garage Conversion ADU Costs in Kendall, FL
Plan on $45,000 to $130,000 for a permitted conversion in Kendall, with most attached-garage projects landing in the $60,000 to $95,000 band. The spread is real and it’s driven by five things, not by “pricing varies.”
- Garage size: a one-car garage under 250 square feet sits at the low end; a two-car garage near 400 square feet adds framing, drywall, flooring, and HVAC capacity in proportion.
- Bathroom and kitchenette scope: adding a full bath means trenching the slab for drain lines. A half bath or a wet-bar setup can save a meaningful chunk.
- Structural work: some garages need a beam where the old opening was, upgraded ceiling framing, or a raised floor assembly. That’s where budgets move most.
- Electrical service: if the existing panel has no room for the new circuits, a service upgrade gets added to the scope.
- Finish grade: builder-grade flooring and paint versus tile throughout and semi-custom cabinetry is a $10,000-plus swing on its own.
A written estimate from us breaks out each of those lines so you can see what you’re buying. What’s typically not in the base number: furniture, appliances beyond the kitchenette, landscaping around a new exterior entry, and any HOA architectural review fees. Florida’s storm and impact requirements are already baked into our quotes, not added later as a change order.
See the difference
Before
After
Before
After
Before
AfterWhat Kendall Homes Specifically Do to This Job
Kendall is a built-out corner of unincorporated Miami-Dade west of the Turnpike, and that shapes this work more than anything else. Nearly every project here is a rebuild of an already-improved lot, not a ground-up build. The housing stock is mostly 1970s-to-1990s concrete block homes, many with barrel-tile or shingle roofs, which means the garage you’re converting has a slab poured decades ago and framing that may not match current practice. We see slab moisture issues, undersized electrical panels, and low ceiling clearances in garages off Kendall Drive and through the tract neighborhoods near The Crossings and Three Lakes. Because it’s unincorporated, permitting runs through Miami-Dade County rather than a city building department, and the county’s product-approval and HVHZ paperwork is a genuine part of the schedule; the paperwork question comes before the price question here, and it should. Subtropical heat and salt-laden air also punish the exterior face of a former garage door opening, which is why we spec coated fasteners and impact-rated assemblies rather than assuming the original materials will hold.
Serving Kendall, FL – Our Local Coverage Area
We serve Kendall and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – Garage Conversion ADU in Kendall
Most converted garages in Kendall take 3 to 5 months from permit submittal to certificate of occupancy, with construction itself running 10 to 16 weeks. The biggest schedule wildcard is Miami-Dade County plan review and inspection availability, which we track and schedule for you. Call (844) 761-9356 for a realistic timeline for your garage.
Yes. A Garage Conversion ADU requires a Miami-Dade County building permit, because you’re adding habitable space, mechanical, electrical, and plumbing. Converting without one can force a tear-out later and complicate any future sale. We pull the permits and manage the inspections.
Sometimes. If the garage already sits adjacent to a bath or laundry wall, a wet-bar or half-bath layout can avoid significant trenching. Full baths and relocated walls almost always require structural and plumbing work, which is where the budget jumps. We’ll tell you honestly which category your garage falls into during the free estimate.
The range is $45,000 to $130,000, with most projects between $60,000 and $95,000. Size, bathroom scope, structural work, electrical service capacity, and finish grade are the five variables that set the number. Call (844) 761-9356 for an exact written quote – estimates are free.
Every Garage Conversion ADU we build is covered by our 730-Day Done Right Promise: if it’s not done right, we make it right. That covers workmanship on framing, rough-in, and finishes for two full years, well beyond the typical one-year contractor warranty.
Get a Free Estimate for Your Garage Conversion ADU in Kendall
Call (844) 761-9356 and we’ll set up a free on-site estimate and design consult at your Kendall home. We walk the garage, measure, check the panel and slab, and talk through layout and finish options before any number appears. You’ll get a written, line-item scope of work with permits and inspections spelled out, and pricing that doesn’t move once work starts. If your project grows into a wider scope, our Home Additions & ADU service covers the full range, and many Kendall homeowners pair this with Backsplash, Tile & Flooring in Kendall for the interior finishes. You can also see everything we do across Kendall and the surrounding neighborhoods like Richmond Heights and Sunset.