Tub-to-Shower Conversion in Richmond Heights, FL: What It Costs and How Long It Takes
A tub-to-shower conversion in Richmond Heights typically runs $3,500 to $10,000 and takes 5 to 10 working days from demo to final inspection. The job means removing the tub, catching and reworking the drain and valve to shower height, waterproofing the walls and pan, setting tile or a solid-surface surround, and swapping the old tub filler for a shower valve and head. It’s a narrower job than a full remodel, and it’s worth pricing carefully. Call (844) 761-9356 for a free on-site estimate.
How we run a tub-to-shower conversion, start to finish
The work below is the actual sequence. We write it out because a conversion has more hidden steps than most homeowners expect, and knowing the order keeps you from being surprised by day three.
Stage 1: Tear-out and structural check. We remove the tub, the surround, and the old valve trim. This is where we find out what’s underneath: water damage to the subfloor and wall studs, previous patch jobs, and whether the drain sits where the new pan needs it. In Richmond Heights ranch homes, this is often the day that decides the whole budget. About a day.
Stage 2: Plumbing rework. The tub drain sits low; a shower drain sits at pan depth. We cut and re-plumb the drain line, raise and replace the mixing valve to shower height, and add blocking for grab bars if you want them. This is the stage where moving the drain to the center of the alcove is a real decision, not an assumption. One to two days.
Stage 3: Waterproofing. This is the part you’ll never see and the part that decides whether the shower holds up. We bond waterproofing membrane or a cement board system to the walls, then build a sloped pan and seal the seams and corners. No tile goes up until this is done and dried. One to two days.
Stage 4: Tile and finish. We set the wall tile and floor tile, grout, then install the shower valve trim, head, and any glass. Budget two to four days here depending on tile size and pattern – large-format tile goes faster than a small mosaic, and a framed glass door takes longer to measure and hang than a curtain rod ever would.
Stage 5: Inspection and final walkthrough. A permitted conversion gets a plumbing inspection and, where the pan is new, a pan check before tile goes over it. We schedule the inspection, walk the finished shower with you, and hand over care instructions. One to two days for the inspection plus your walkthrough.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The choices you’ll actually make on this job
You’ll decide four things before the tile order goes in, and each one moves the price. Here’s the honest trade-off on each.
- Wall finish: tile vs. solid surface. Ceramic or porcelain tile runs roughly $800 to $2,500 in materials for a standard alcove and lasts decades if the waterproofing is right. A solid-surface surround (acrylic or composite) is cheaper and faster to install but looks like what it is, and seams can collect moisture over time. Porcelain tile is the choice most Richmond Heights homeowners make when resale value matters.
- Pan: tile-in vs. prefab. A tile pan lets you match the floor to the walls and lets us slope it precisely, but it’s slower to build and needs that pan inspection. A preformed pan installs in an afternoon and costs less, with a narrower choice of sizes.
- Fixture brand and finish. A Kohler or Moen valve and trim set gives you a reliable cartridge and replacement parts you can still buy in five years. A cheap builder-grade valve is disposable. On a conversion, spend here: a leaking valve behind new tile is the most expensive cheap decision in the job.
- Glass vs. curtain. A fixed glass panel or framed door adds a few hundred dollars to over a thousand, and it opens the shower visually. A curtain rod is free and lets you change the look later. Neither is wrong – the door is mostly a resale and looks decision.
One thing we don’t put on a wall in a wet shower: painted drywall behind tile. It fails. Every finished surface sits on a waterproof membrane or a cement board system, and we’ll show you which before we close it up.
What Tub-to-Shower Conversion costs in Richmond Heights, FL
Most Richmond Heights tub-to-shower conversions land between $3,500 and $10,000. A tight alcove conversion with a prefab pan and standard ceramic tile sits at the low end. A larger walk-in footprint with a center drain, large-format porcelain, a frameless glass panel, and a Kohler valve lands near the top. The range sits inside the broader Bathroom Remodeling in Richmond Heights budget of $9,000 to $28,000 when you’re reworking the rest of the room too.
What pushes you to the high end: relocating the drain or moving a wall, hidden water damage at tear-out, a valve change that requires opening the adjacent wall, upgrading from standard ceramic to large-format or marble-look tile, and glass versus a curtain. What keeps you near the low end: keeping the drain where it is, a standard-size alcove, prefab pan, and stock tile.
A written estimate from us lists demo, plumbing rework, waterproofing, tile labor and materials, fixtures, glass, disposal, and the permit fee as separate lines with a fixed total. The number you see is the number you pay – no change orders unless you change the scope after work starts.
See the difference
Before
After
Before
After
Before
AfterWhat Richmond Heights homes specifically do to this job
Richmond Heights has a distinctive housing mix. It’s one of South Florida’s historically Black communities, and its construction identity was shaped by mid-century ranch housing built on post-war slabs over the shallow limestone that runs along the Redland ridge. In a 1950s-to-1970s concrete-block ranch on a slab, the tub sits on a poured floor, not a framed floor, so our crew has to break out and re-pour around the new drain instead of dropping it through wood framing. That adds a day and some concrete work to the schedule, and we check the slab for cracks or prior water intrusion before we set the pan.
The area’s high water table and frequent summer downpours matter here too. We specify a cementitious waterproofing system and a properly sloped pan because our humid summers punish any pan that isn’t perfectly pitched. Infill construction has also brought new custom builds in alongside the original ranch homes, and those newer homes often have framed floors and different framing behind the shower. We size the work to the actual house, not to a template. Groundwork Construction Co. covers Richmond Heights and ZIP 33176 – you can see the full Richmond Heights service area here – and our crews are equally comfortable with renovation tie-ins in an original ranch and structural work in a new build.
Serving Richmond Heights, FL – Our Local Coverage Area
We serve Richmond Heights and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked: Tub-to-Shower Conversion in Richmond Heights
Most conversions take 5 to 10 working days. Demolition and plumbing rework take two to three days, waterproofing takes one to two, tile and finish take two to four, and the inspection and walkthrough add one or two more. Scheduling depends on your tile arriving on time and the inspection slot. Call (844) 761-9356 to lock in a start date.
Yes, in most cases – a drain relocation, valve change, and new shower pan are plumbing changes that get permitted and inspected. We pull the permit and schedule the inspection for you. Skipping it can complicate a future sale and, more importantly, hides the one step that protects your floor from water damage. Call (844) 761-9356 to talk through your specific setup.
Often yes. If the existing drain and valve can stay where they are, you save the plumbing rework cost and a day of labor. The trade-off is that the shower sits in the tub’s footprint, which is narrower than a true walk-in. If you want a larger footprint or a center drain, the plumbing has to move, and that’s where the cost and the schedule grow. Call (844) 761-9356 and we’ll tell you which is realistic for your bathroom.
Between $3,500 and $10,000, depending on size, materials, and whether the plumbing and structure move. Hidden water damage, a larger footprint, large-format tile, and glass all push toward the top of that range. Call (844) 761-9356 for an exact quote – the estimate is free.
Every conversion carries our 730-Day Done Right Promise. If anything we installed fails, we make it right – that’s the written guarantee, and it covers workmanship on the waterproofing, tile, and fixture install. Waterproofing and tile failures usually show up within the first two heating-and-storm seasons, and that guarantee window covers them. Call (844) 761-9356 with any warranty question.
Schedule a free tub-to-shower conversion estimate in Richmond Heights
Call (844) 761-9356 for a free on-site estimate on your tub-to-shower conversion in Richmond Heights. A live person answers, day or night. We’ll measure the alcove, look at the drain and valve, talk through tile and glass options, and hand you a written line-item quote with a fixed total – 0% financing for 18 months is available, plus $1,000 off projects over $10,000. Groundwork Construction Co. handles the full scope from demo to final inspection, and our bathroom remodeling service is here when the job grows past the shower.
Written by the team at Groundwork Construction Co.