Tub-to-Shower Conversion in The Hammocks, FL: What It Costs and How Long It Takes
A tub-to-shower conversion in The Hammocks runs $3,500 to $10,000, and most jobs are finished in 5 to 10 working days from demo to final inspection. The work means pulling the old tub and its surround, reworking the drain and valve to shower position, waterproofing the wet area, and setting a new shower pan, tile or panel walls, and glass. In this part of The Hammocks, where almost every house is a 1980s-to-2000s CBS tract home, the framing and drain rough-in are usually simple – the surprises live in 20-to-30-year-old tile and valve cartridges. Call (844) 761-9356 for a free on-site estimate.
How a Tub-to-Shower Conversion Actually Runs, Stage by Stage
We don’t hand you a start date and disappear. You’ll know what happens on day one, what’s decided by day three, and when the inspector shows up. Here’s the sequence a conversion in The Hammocks follows.
Stage 1: Site visit and written scope (before any work)
We measure the alcove, check the drain location and valve type, and open the wall behind the tub if you want to move the shower head or add a niche. You decide the footprint – keep it in the same alcove or reclaim space – and whether the valve stays where it is. The estimate comes back line-itemed: demo, rough-in, waterproofing, tile or panels, glass, permit. No allowances that balloon later. This usually takes 45 to 60 minutes.
Stage 2: Demo and rough-in (days 1 and 2)
We protect the floor and the hall, then pull the tub, surround, and old backer. In these homes that means breaking out the original 4-inch tile and the mud set behind it, which is dusty work and the noisiest part of the job. Once it’s open we inspect the drain and valve for corrosion and swap out what’s failing. If the drain needs to move off center or the valve needs a new rough-in, this is the day.
Stage 3: Waterproofing and inspection (day 3)
The pan gets set, the walls get backer board and a bonded waterproofing membrane, and the seams get taped and sealed. In Miami-Dade the shower pan and valve rough-in are inspected before tile goes on, so we schedule that inspection and don’t cover anything until it passes. You’ll hear from us the day before; you don’t need to be home, but you can be.
Stage 4: Tile, panels, or slab walls (days 4 through 7 or 8)
This is where your choices show up. A 12×24 porcelain tile with a linear drain and a built-in bench is a 4-to-5-day set; a large-format slab wall is faster but needs a precise template; a prefab acrylic or composite panel system is a 2-day install and much easier to clean. Grout goes last, and we seal it before the glass goes in. You’ll pick grout color and trim profiles at this stage.
Stage 5: Glass, fixtures, and final inspection (days 8 through 10)
The frameless or semi-frameless door goes on, we set the trim kit and shower head, seal the edges, and do a leak test. Then the final inspection, a walkthrough with you, and a signed punch list. That’s where the 730-Day Done Right Promise starts – if anything about the workmanship fails, we come back and make it right. Most conversions in The Hammocks wrap inside two working weeks.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices You’ll Make – and What Each One Really Costs You
Nothing about a conversion is one-size. These are the decisions that move the number and the feel of the finished shower.
- Tile vs. panels vs. slab. Porcelain tile is the most forgiving on budget and the most customizable; a linear drain and a niche add a few hundred dollars. Composite panels cost less and clean up faster but read as builder-grade. Large-format slab walls look the most custom and cost the most. If you’ve seen a frameless glass enclosure you like, you’ll likely want the tile and slab to match.
- Drain style. A center drain is the default and the cheapest. A linear drain sits at one end, slopes one plane of the pan, and adds cost but makes the floor feel larger and easier to squeegee.
- Glass. A frameless door with a Mr-Glass panel or similar is the finish most homeowners want and adds $800 to $1,800 over a framed door. Semi-frameless is a middle path.
- Valve and trim. A pressure-balance valve is standard. A thermostatic valve and rain head cost more but hold temperature better in a house where the kitchen faucet and laundry run at the same time.
- Bench, niche, and grab bars. A built-in bench is a structural add and needs blocking; a niche is a waterproofing detail. Grab bars (and the blocking behind them) are worth deciding now, not later.
- Door and window trim. If the bathroom window is original to the house, we often set a Therma-Tru or ViewLux unit with impact glazing while the wall is open – it’s cheaper to do once.
What a Tub-to-Shower Conversion Costs in The Hammocks, FL
Plan on $3,500 to $10,000 for a tub-to-shower conversion in The Hammocks. The line-item ranges we quote look like this:
- Demo and haul-off: $400 to $900
- Drain and valve rough-in (if moved or replaced): $700 to $2,200
- Waterproofing, pan, and backer: $600 to $1,500
- Tile, panels, or slab walls: $1,200 to $4,000
- Glass door and panel: $800 to $1,800
- Fixtures, trim, and shower head: $300 to $1,200
- Permit and inspection: $250 to $600
The low end is a same-footprint acrylic or panel conversion with a framed door and a center drain. The high end is a larger custom pan, slab walls, a thermostatic valve, a linear drain, and a frameless Mr-Glass enclosure – often $8,000 to $10,000. A permit that requires opening and re-inspecting the wall cavity, or a valve that has to be relocated because the old tub’s plumbing sits behind a finished wall, pushes you up. What’s included: all labor, materials, permit, inspection, and the 730-Day Done Right Promise. What isn’t: new floor tile outside the shower footprint, vanity or toilet work, and any structural change to the room – those are quoted separately. Call (844) 761-9356 for an exact, written estimate; the number you see is the number you pay.
See the difference
Before
After
Before
After
Before
AfterWhat The Hammocks Homes Specifically Do to This Job
The Hammocks was built almost entirely between the 1980s and 2000s as a master-planned, unincorporated Kendall-area subdivision. That means nearly every house on your block is the same CBS construction, the same stucco, and the same vintage – so the tub and its tile surround are 25 to 35 years old, and they fail the same way across whole blocks. We regularly see the original 4-inch wall tile pop loose, grout lines gone, and the tub surround leaking into the wall behind it. When a bathroom wall is opened for a conversion, we look for the water staining and rusted fasteners that subtropical humidity and hurricane-season wind-driven rain push into these homes. Miami-Dade’s High-Velocity Hurricane Zone rules apply to any glass and window product we set – that’s why Mr-Glass and Therma-Tru or ViewLux get specified, and why we pull permits rather than skip them. The Hammocks is also HOA-heavy; decorative glass inserts and shower door changes usually don’t require approval, but a window change or exterior vent does, so we tell you in writing which items you should pre-clear with your board. Homeowners planning a full Bathroom Remodeling in The Hammocks often fold the shower into that scope, and we also handle The Hammocks neighbors in Country Walk, The Crossings, and Kendall West. If you’re re-roofing while the dust is flying, homeowners often pair this with Metal Roofing in The Hammocks or Tile Roofing in The Hammocks – the block-by-block permit run here makes it sensible to do both in one season.
Serving The Hammocks, FL – Our Local Coverage Area
We serve The Hammocks and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – Tub-to-Shower Conversion in The Hammocks
Most take 5 to 10 working days from demo to final inspection, with 2 to 3 weeks of calendar time once you factor in the Miami-Dade inspection schedule. A prefab panel conversion can finish in 4 to 5 days; a custom tile and slab conversion usually lands closer to 10. Call (844) 761-9356 for an exact schedule on your bathroom.
Yes – relocating or replacing the shower valve and the drain rough-in requires a plumbing permit and a shower pan inspection in Miami-Dade. We pull the permit and meet the inspector ourselves. Skipping it can stall a future sale and voids the warranty on the rough-in, so we don’t offer that shortcut. Call for a free estimate that includes permit cost.
Usually, yes. If the drain is centered under the tub and the valve sits on the same wall, the shower can be built in the same alcove with no structural change – that’s the $3,500 to $6,000 end of the range. Moving the drain off center, adding a bench, or widening the opening is where the number climbs. We confirm this on the first visit.
Expect $3,500 to $10,000, and the price you sign is the price you pay – we don’t do change orders on work we scope correctly. If we open the wall and find rotted framing or a failed valve, we stop, show you, and quote the fix in writing before touching it. Call (844) 761-9356 for a written estimate.
Every conversion is covered by the 730-Day Done Right Promise – if the workmanship fails, we make it right for two years. Manufacturer warranties on fixtures and glass run alongside it. Our technicians have up to 12 years of experience, are background-checked, and arrive in uniform. Call (844) 761-9356 to talk through the details.
Get a Free Estimate for Your Tub-to-Shower Conversion in The Hammocks
Call (844) 761-9356 and a live person answers, any hour. We’ll set a free on-site estimate, measure the alcove, check the drain and valve, and leave you with a written line-item quote and a realistic start date. If you’re weighing a bigger project, our Bathroom Remodeling service covers the rest of the room. No pressure, no bait pricing – just a number you can plan around.