Full Bathroom Remodeling in Country Walk, FL: What the Job Actually Involves
A full bathroom remodeling in Country Walk typically runs $9,000 to $28,000 and takes three to six weeks of working time, depending on how much plumbing and electrical you move. That’s a complete gut: tub or shower out, tile, vanity, toilet, lighting and vent fan replaced, with the room brought back to code. Call (844) 761-9356 and we’ll walk the room with you and put the number in writing before anything gets ordered.
How a full bathroom remodel moves from demo to final walkthrough
We’ve done enough of these in the Country Walk area to know the calendar is where remodels fall apart. Here’s the sequence we hold to, and where you make decisions.
Stage 1: Site protection and demolition (days 1 – 2)
Floors in the path get protected, water is shut off at the fixture stops, and the room comes down to studs and slab on day one. We set a temporary dust barrier at the door. By the end of day two you have an empty shell. Your decision here is already made: fixture layout and finish schedule should be locked before demo, not after.
Stage 2: Rough-in and inspection (days 3 – 5)
If we’re relocating the shower valve, adding a dedicated exhaust fan, or moving the toilet flange, this is when it happens. Miami-Dade requires inspection on the plumbing and electrical rough-in before walls close, and that inspection is scheduled at the rough stage, not the end. You’ll sign off on any layout changes from the original plan at this point, because after the inspection, moving a drain means re-opening the floor.
Stage 3: Waterproofing and backer board (days 6 – 8)
This is the stage most remodels get wrong in South Florida. Cement backer board and a bonded waterproofing membrane go in the wet areas before a single tile is set. In a house with the humidity Country Walk runs from May through October, a shower built without a proper waterproof layer will grow mold behind the tile within a few seasons. Your decision: whether to add a shower niche, a bench, or a linear drain, all of which need to be framed and waterproofed now, never later.
Stage 4: Tile, grout, and trim (days 9 – 20)
Wall tile, floor tile, grout, caulk at the changes of plane. Large-format porcelain takes longer to set than a 4-inch ceramic. If you chose a decorative mosaic or a niche with a border, add a few days. Nothing for you to decide here except accepting the tile layout before the first course goes up.
Stage 5: Fixtures, glass, and punch (days 21 – 30+)
Vanity, countertop, toilet, faucet, shower trim, mirror, lighting, exhaust fan, and shower glass. Glass is ordered after tile is measured, so there’s a fabrication lead time on the enclosure. Final walkthrough, then the punch list gets closed before we call it done.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The options you’ll actually choose between in Country Walk
A full bath gives you more choices than any other room of its size, and each one has a cost and a durability story. Here’s how we talk through them with homeowners.
- Vanity top: Silestone quartz gives you a non-porous surface that shrugs off South Florida humidity and won’t need sealing. Honed marble looks richer but stains and etches with everyday use. Laminate is the budget pick and does fine in a hall bath.
- Fixtures: Kohler and Moen both make trim lines that hold up to years of hard water. A budget faucet from a big-box shelf is the first thing to fail in a shower. Spend here first.
- Floor tile: Porcelain is dense, slip-resistant when matte-finished, and handles the moisture swings. Natural stone needs sealing every year or two and shows etching.
- Wet-area construction: A properly waterproofed cement board system costs more than greenboard but is the difference between a shower that lasts and one that gets torn out. Never value-engineer this line.
- Ventilation: Code calls for a bath fan vented to the exterior, not into the attic. In Country Walk’s heat and humidity, a correctly sized fan is what keeps stucco and drywall from holding moisture.
What Full Bathroom Remodeling costs in Country Walk, FL
The realistic range for a full bathroom remodeling in Country Walk is $9,000 to $28,000. That’s the honest spread. Five variables decide where your job lands:
- Room size and fixtures: A 5-by-8 hall bath stays at the low end. A primary bath with a double vanity, a large shower and a separate water closet pushes toward the top.
- Existing condition: Undiscovered rot, failed plumbing, or a slab drain that needs re-cutting adds cost once the walls are open. We price what we can see and flag what we can’t.
- Moving plumbing or electrical: Keeping the toilet and shower where they are saves real money. Relocating a drain, adding circuits, or moving the exhaust fan changes the labor and the permit scope.
- Material grade: Porcelain and Silestone at one end, imported stone and custom glass at the other. Faucet and fixture tier alone can swing the number by a few thousand.
- Permit and inspection scope: A cosmetic refresh needs less paperwork than a layout change with new drain lines. We pull the permits the job requires, so it’s built correctly and doesn’t surface as a problem when you sell.
A written line-item estimate tells you exactly what’s included: demo, rough-in, waterproofing, tile, fixtures, glass, paint, and final cleanup. What’s typically not included is hidden damage behind the walls, upgrades you add mid-job, or a permit for structural changes you didn’t plan on. We quote those in writing before moving forward. That’s the upfront pricing, no-surprises standard we hold to on every Country Walk project.
See the difference
Before
After
Before
After
Before
AfterWhat Country Walk homes specifically do to this job
Country Walk is a master-planned west Kendall subdivision built out mostly through the 1980s and ’90s, so the work here is renovation, not new construction. The typical home is CBS concrete block with stucco, a barrel-tile or shingle roof, and the interior finishes the builder installed decades ago. That means most of the bathrooms we open up still have the original cast-iron or early PVC plumbing and a builder-grade exhaust fan venting into the attic. Those fans are a real problem in this climate, and we replace them as a matter of course. What’s different about a Country Walk bathroom remodel is the approval layer: Miami-Dade County permitting and the Country Walk HOA’s architectural review both apply, and the HOA review has its own timeline you need to budget for before demo begins. Because the lots are uniform and closely spaced, that same review governs anything that touches the exterior envelope, from a window change to a structural wall. Homeowners here often pair an interior remodel with Roof Repair in Country Walk if the tile roofs are aging, or Roof Replacement & Installation in Country Walk when a whole street of late-’80s tile is hitting end of life together. If the bathroom work is part of a wider scope, see our Bathroom Remodeling in Country Walk page for the broader picture, or our Bathroom Remodeling service hub for the full menu. We cover the whole Country Walk community and the surrounding area.
Serving Country Walk, FL – Our Local Coverage Area
We serve Country Walk and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked – Full Bathroom Remodeling in Country Walk
Plan on three to six weeks of working time from demo to final walkthrough. A straightforward gut of a 5-by-8 bath finishes closer to three weeks, while a primary bath with a layout change and custom glass runs six. The Country Walk HOA architectural review can add lead time before work starts, so build that into your schedule. Call (844) 761-9356 and we’ll give you a realistic timeline once we’ve seen the room.
Yes, any full bathroom remodeling that touches plumbing, electrical, or mechanical requires a Miami-Dade County permit and inspection. Cosmetic-only work like paint or swapping a faucet typically doesn’t. We pull the permits the job requires and pass inspection, which protects you at resale. Call us for a written scope that spells out the permit line.
Yes, and keeping the toilet and shower where they sit saves meaningful money. Leaving the drain and supply lines in place avoids re-cutting the slab and shortens the job. You still get a full gut, new tile, new vanity, and new fixtures. Call (844) 761-9356 to talk through what a no-relocation layout would look like in your Country Walk home.
The range is $9,000 to $28,000 depending on size, whether you move plumbing, and the finish tier you choose. A hall bath with porcelain and a Silestone or Caesarstone top sits near the bottom; a primary bath with imported stone and custom glass sits near the top. Call (844) 761-9356 for an exact line-item quote, and estimates are free.
Every full bathroom remodeling project we complete is covered by our 730-Day Done Right Promise. If something we built isn’t right, we make it right, and the guarantee runs two full years. That’s one of the longer workmanship warranties in residential construction. Call us to see the terms in writing before you sign.
Ready for a written estimate on your Country Walk bathroom?
Call Groundwork Construction Co. of The Hammocks at (844) 761-9356 to schedule your free on-site estimate. We walk the room with you, measure, and talk through the layout and finish options. You leave the visit with a written line-item quote and a clear timeline. Calls are answered by a live person around the clock. Financing is available at 0% for 18 months, plus $1,000 off projects over $10,000.