What Full Bathroom Remodeling in Westwood Lakes, FL actually involves
Full Bathroom Remodeling in Westwood Lakes, FL means gutting a bathroom down to the studs and rebuilding the wet zone, floor, fixtures, ventilation and electrical to current code, and it typically runs $9,000 – $28,000 depending on size and finish level. A full gut of a standard hall or primary bath takes about 4 to 6 weeks from demo to final inspection. Call (844) 761-9356 for a free on-site estimate.
How we run a full bathroom gut, stage by stage
Every full bathroom we rebuild follows the same sequence, and the sequence is what keeps a 4-to-6-week job from sliding into three months. Here’s what actually happens.
Stage 1: Layout, selections and permits (days 1-7)
Before anything gets smashed, you lock the layout: where the toilet, vanity, shower and tub land. This is when you pick tile, stone, fixtures and glass, because lead times on a Silestone or Caesarstone vanity top can run two weeks and you don’t want the job waiting on a slab. We pull the Miami-Dade County permit in this window. Decide now: keeping the existing footprint or moving walls.
Stage 2: Demo and rough-in (days 7-12)
We protect the floors, bag out old tile, tub and drywall, and get down to studs. Here’s where surprises surface in Westwood Lakes homes: rotted subfloor near the shower, old galvanized supply lines, or a drain that was never vented right. The plumber and electrician rough in new supply, drain and GFCI circuits, then the inspector signs off on the rough before anything closes up.
Stage 3: Waterproofing and prep (days 12-18)
Cement board goes up and the shower gets a bonded waterproofing membrane, not just plastic sheeting. This is the step homeowners can’t see and shouldn’t skip in South Florida’s humidity. Decide: niche placement, bench, and whether you’re doing a curbless entry.
Stage 4: Tile and finishes (days 18-32)
Floor tile, wall tile, grout, then vanity, mirror, lighting and toilet. A Kohler or Moen faucet set goes in here. Expect the longest stretch of the job to be tile work – it’s slow by nature and rushing it shows.
Stage 5: Glass, trim and final inspection (days 32-42)
Shower glass, door hardware, paint touch-ups, and the final plumbing and electrical inspection. We walk it with you, punch-list in hand, before you pay the final draw.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The options you’ll choose between before demo starts
Most of the cost difference between two Westwood Lakes bathrooms of the same size comes down to these decisions, not labor.
- Tile vs. large-format porcelain: Standard ceramic tile runs a few dollars a square foot; large-format porcelain or natural stone costs two to four times that and needs a flatter substrate. Stone holds up longer and looks better in a small bath; porcelain is easier to maintain.
- Quartz vanity top vs. granite: Quartz (Silestone, Caesarstone) is non-porous and doesn’t need sealing, which matters in a humid bathroom. Granite is cheaper on some slabs but wants resealing yearly.
- Framed vs. frameless glass: Frameless looks cleaner and is easier to squeegee; framed is more forgiving on an out-of-square opening, which many 1960s CBS homes have.
- Cast iron vs. acrylic tub: Cast iron holds heat and lasts decades but adds weight and cost; acrylic is lighter and cheaper, and can flex over time.
- Keeping the footprint vs. moving plumbing: Same layout saves real money. Moving a drain or supply line across the slab adds cost and rough-in time.
What Full Bathroom Remodeling costs in Westwood Lakes, FL
Full Bathroom Remodeling in Westwood Lakes runs $9,000 to $28,000. A straightforward hall bath with stock finishes lands near the low end; a primary bath with a custom shower, quartz vanity and moved plumbing lands near the top.
| Line item | Typical range |
|---|---|
| Full bathroom remodel (gut to finish) | $9,000 – $28,000 |
| Vanity installation | $800 – $3,000 |
| Walk-in shower installation | $4,500 – $12,000 |
| Shower replacement | $3,000 – $8,500 |
What pushes a job to the high end: square footage, moving plumbing or electrical, structural changes like widening a doorway, premium stone and glass, and permit scope that includes relocating fixtures. What keeps it low: keeping the footprint, stock tile, and reusing a sound tub.
A written estimate covers demo, rough-in, waterproofing, tile, fixtures, trim and the final inspection. It typically does not cover hidden rot behind the wall or a slab repair found mid-demo – and those we price before we touch them, not after. No-hassle upfront pricing means the number you see is the number you pay.
See the difference
Before
After
Before
After
Before
AfterWhat Westwood Lakes homes specifically do to this job
Westwood Lakes is a built-out, post-war suburb in ZIP 33165 where nearly every bathroom project is a renovation on a late-1950s-to-1970s CBS lot, not new construction. That changes the work. These concrete-block homes sit on slabs with original terrazzo floors, and behind the bathroom wall you often find 1960s galvanized pipes and a drain vented to an older code standard – so a gut almost always means rough-in work, not just new tile.
The bigger local reality is water. Low-lying land just west of the urban core, heavy summer downpours, and a wet season that runs June through November mean bathrooms here fail at the same seams: the shower pan, the wall-to-floor junction, and the window opening. Original jalousie frames on these homes were never built for today’s storm intensity, and we’ve pulled more than one vanity to find mold creeping up from a slow leak behind it. We check the roof-wall junction and window flashing on the same visit, because a bathroom leak often starts at the roof above it. That’s also why homeowners often pair a bathroom rebuild with Roof Repair in Westwood Lakes when the same water intrusion shows up top and bottom – and if the roof is at the end of its life, Roof Replacement & Installation in Westwood Lakes is worth pricing together.
Miami-Dade County’s post-Surfside recertification and 40-year inspection rules for aging concrete-block homes also mean your permit and inspection history matters. We pull the permits and pass the inspections, and we walk the recertification angle with you if the home is nearing its 40-year mark. Covering Westwood Lakes means we work this housing stock routinely.
Serving Westwood Lakes, FL – Our Local Coverage Area
We serve Westwood Lakes and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked – Full Bathroom Remodeling in Westwood Lakes
A full bathroom gut typically takes 4 to 6 weeks from demo to final inspection. Small baths with stock finishes move fastest; custom tile, glass lead times and any plumbing relocation add days. Call (844) 761-9356 for a timeline on your exact bath.
Yes – moving plumbing, electrical or walls requires a Miami-Dade County permit, and a full gut with a rough-in inspection almost always triggers one. We pull the permits and schedule the inspections for you. Call (844) 761-9356 with questions on your project.
Yes, and keeping the existing footprint is the single biggest way to hold the budget down. If the drain and supply locations work, we leave them and spend the money on tile and fixtures instead. Call (844) 761-9356 to hear what stays and what moves.
Expect $9,000 to $28,000, with the low end for a simple hall bath and the high end for a primary bath with custom shower, quartz vanity and moved plumbing. Call (844) 761-9356 for an exact quote – estimates are free.
Every full bathroom we build is covered by our 730-Day Done Right Promise – if it’s not done right, we make it right. That’s one of the longest workmanship guarantees in residential construction. Call (844) 761-9356 to start.
Get a free estimate for your Westwood Lakes bathroom
Call (844) 761-9356 to schedule a free on-site estimate for Full Bathroom Remodeling in Westwood Lakes. We’ll measure the bath, talk through layout and finish options, and hand you a written line-item price with no surprises – the number you see is the number you pay. Live person, 24/7. Ask about 0% financing for 18 months and $1,000 off projects over $10,000.