Garage Conversion ADU in Three Lakes, FL: What It Takes and What It Costs
A garage conversion ADU in Three Lakes, FL typically runs $45,000 – $130,000 and takes 10 to 16 weeks from permit to final inspection, depending on whether you’re keeping the existing slab and walls or moving plumbing and re-framing. The work turns your attached garage into a permitted, wind-rated living unit – not a finished room, but a legal secondary dwelling with its own entry, kitchenette, bath, and impact-rated fenestration. Call (844) 761-9356 to schedule a free on-site estimate.
How the Conversion Actually Runs, Stage by Stage
A garage conversion touches structure, mechanical, and waterproofing in a tight footprint, so the sequence matters more than the finish selections. Here’s what a real three-to-four-month schedule looks like.
- Stage 1 – Assessment and design (weeks 1 – 2). We open the existing slab to check for moisture and cracking, trace the aluminum wiring and any drain lines, and measure the garage door opening against the setback and lot-coverage rules your lot allows. You decide the unit’s layout, entry door location, and whether the kitchenette is a full range or a two-burner-and-fridge setup. This is also when we confirm wind-load and product-approval requirements with Miami-Dade before a single line is drawn on the permit.
- Stage 2 – Permits and demo (weeks 2 – 4). Plans go to Miami-Dade County for the building, electrical, plumbing, and mechanical permits. Once issued, we remove the overhead door, frame the new wall with impact-rated glazing or solid construction, and strip the old drywall if it’s there. You’ll decide the exterior finish – stucco to match the house or a contrasting cladding – before this stage closes.
- Stage 3 – Rough-in (weeks 4 – 7). New electrical panel tie-in or subpanel, dedicated circuits, plumbing for the bath and kitchenette, and a mini-split or tie-in to the house HVAC. The county inspects rough framing, electrical, and plumbing before anything gets closed up. You decide the mini-split versus central tie-in here, and that choice affects budget and future utility bills.
- Stage 4 – Insulation, drywall, and weatherproofing (weeks 7 – 10). Spray foam or batt insulation to the county’s envelope spec, drywall, and the new exterior wall’s waterproofing and flashing. This is the stage where wind-driven rain testing on the wall assembly matters, and where we close up the tie-in to the main roof edge.
- Stage 5 – Finishes and final inspection (weeks 10 – 16). Impact-rated entry door hung, flooring laid, kitchenette and bath fixtures set, paint and trim. The final inspection covers everything from the door’s product-approval label to the smoke and CO detectors. You walk the unit with us before the certificate of occupancy is issued.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices You’ll Actually Be Weighing
Most of the budget swing lives in four decisions. Here’s the honest trade-off on each.
- Entry door: impact-rated glazed vs. solid. A Therma-Tru or Mr-Glass impact door with laminated glass gives you light and a clean look, costs more than a solid door, and carries the HVHZ product-approval label the county wants to see. A solid impact-rated door is cheaper and more private but closes the unit off from daylight. For a rental unit, the glazed version is usually the better call.
- Exterior wall where the garage door was. You can frame a new wall with an impact window (a ViewLux unit works well here) or leave the opening wide and set a full-height impact slider. The slider feels bigger and better for a studio layout; the framed wall with a standard window costs less and is easier to insulate well.
- Climate control: mini-split vs. tie-in. A ductless mini-split is simpler to permit, gives the tenant their own thermostat, and costs less to install. Tying into the house system is cleaner on the exterior and one less piece of equipment to service, but it loads the existing unit and often requires upsizing.
- Flooring and trim. Luxury vinyl plank holds up to moisture and is the most common choice in a converted slab-on-grade space. Tile costs more but handles humid garages well, and homeowners often pair the unit’s tile work with Backsplash, Tile & Flooring in Three Lakes on the main house at the same time.
What a Garage Conversion ADU Costs in Three Lakes, FL
Expect $45,000 – $130,000 for a permitted garage conversion ADU in Three Lakes, with most projects landing in the $60,000 – $95,000 band. The low end keeps plumbing close to existing lines and uses a simple rectangular layout; the high end adds a full bath, kitchenette, upgraded impact glazing throughout, and a new subpanel.
Five things push a job toward the top of that range:
- Plumbing distance. Running a drain across the slab to the far corner of the garage can add $4,000 – $9,000 versus setting the bath against the house wall where the main line already runs.
- Electrical. A subpanel and dedicated circuits are routine, but replacing aging aluminum wiring in a 1980s garage adds cost and scope.
- HVAC choice. The mini-split-to-central-tie-in swing is typically a few thousand dollars either way.
- Impact glazing and door count. Every opening needs a rated product with a county approval label, and more openings mean more of the budget.
- Permit scope. A conversion permitted as a true dwelling unit with its own kitchen and bath jumps the review and inspection fees versus a simple rec-room remodel.
A written estimate from us is line-item, not a lump sum. It includes permits, impact products with their approval labels, rough-in, finishes, and cleanup. It typically does not include HOA application fees, landscape repair where the crew ran equipment, or new appliances if you supply them separately. The number you see is the number you pay – no change orders after work starts.
See the difference
Before
After
Before
After
Before
AfterWhat Three Lakes Homes Specifically Do to This Job
Three Lakes is a built-out 1980s – 90s pocket of western Kendall, ZIP 33186, where nearly every project is a remodel on an aging Mediterranean-style concrete-block house – not new ground-up building. That means garage conversions here run headfirst into Miami-Dade County’s product-approval and wind-load rules on a house that’s already 30-plus years old. The original aluminum-frame single-pane windows and the barrel-tile roof are often at or near end-of-life, and because the county requires wind-mitigation features to current HVHZ standards on any permitted work, a garage conversion frequently pulls a re-roof or window upgrade into the same scope.
The original concrete-block garage walls and slab are usually sound, which keeps structural work modest. The failure modes we run into are aging aluminum branch wiring, cast-iron drain lines nearing the end of their service life, and moisture at the slab edge after a storm season. On tight HOA lots, we stage materials in the driveway and plan the impact-door delivery around the community’s rules. Neighbors along the same street are often re-roofing in clusters after a named storm, so we plan our crews around the county’s inspection wave. And because the finished unit needs its own entry with impact-rated glazing and reinforcement, homeowners often pair a conversion with the wider scope on our Home Additions & ADU in Three Lakes page and the kitchenette finish work on Cabinets & Countertops in Three Lakes, which is where the casework and stone go in.
We cover Three Lakes and the surrounding western Kendall communities, including The Crossings, Country Walk, The Hammocks, and Kendale Lakes, so the drive to your job isn’t a six-week wait. See the full service-area map on our Three Lakes page.
Serving Three Lakes, FL – Our Local Coverage Area
We serve Three Lakes and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked Questions
Plan on 10 to 16 weeks from signed contract to certificate of occupancy, with the permit and design phase accounting for the first two to four of those weeks. The finish stage is where most of the schedule risk lives, because impact products have to arrive with their county approval labels intact. Call (844) 761-9356 for a schedule estimate on your specific garage.
Yes – a garage conversion ADU is a permitted dwelling unit in Miami-Dade County, requiring building, electrical, plumbing, and mechanical permits plus final inspection. The county will want to see wind-rated construction and product approvals on the new exterior wall and any glazing. We pull the permits and walk the inspections, so you’re not chasing the county yourself.
Often yes, and that’s the cheapest path. If the bath and kitchenette back up to the house’s existing wet wall, you can avoid a new drain line across the slab and skip reinforcing the mid-span. A full re-layout adds cost but is doable. We’ll trace the existing lines on the first visit and tell you which way your garage leans.
Our range is $45,000 – $130,000, with most Three Lakes projects landing between $60,000 and $95,000. The swing comes down to plumbing distance, electrical condition, HVAC choice, and how many impact-rated openings the unit needs. Call (844) 761-9356 for an exact quote – estimates are free and line-item.
Every garage conversion ADU we build is covered by the 730-Day Done Right Promise – if it’s not done right, we make it right. That’s one of the longest workmanship guarantees in residential construction, and it covers the rough-in and the finishes, not just the parts. If your unit needs service down the road, you call a live person at (844) 761-9356, 24/7.
Get a Free On-Site Estimate for Your Three Lakes Garage Conversion ADU
Call (844) 761-9356 to schedule a free on-site estimate for a garage conversion ADU in Three Lakes. We’ll walk your garage, trace the existing plumbing and electrical, flag any wind-mitigation upgrades the county will require, and hand you a line-item quote with a realistic schedule. No sales pitch, no pressure. This is part of our wider Home Additions & ADU service. Financing is available at 0% for 18 months, and there’s $1,000 off any project over $10,000.
Written by the team at Groundwork Construction Co.