Vanities, Tile & Fixtures in The Crossings: What the Job Actually Costs and Covers
Vanities, tile and fixtures in The Crossings typically run $9,000 – $28,000 for a full tear-out and rebuild of the wet zone, and most jobs finish in two to three weeks of working days. That number covers demolition, waterproofing, floor and wall tile, a new vanity with countertop and sink, and the faucet, mirror and lighting package. Call (844) 761-9356 and we’ll walk your bathroom and put a line-item number in front of you.
How we run a vanity, tile and fixture job, stage by stage
This is a sequence, not a pile of tasks. Each stage has to finish clean before the next one starts, because tile hides everything underneath it.
Stage 1: Demo and rough-in inspection (days 1 – 3)
We pull the old vanity, toilet, tile and drywall down to studs and slab. That’s when we find out what the last remodel left behind, and in a 1990s The Crossings bathroom it’s usually a buried shutoff valve or a flange that’s been leaking quietly. Rough plumbing and electrical get corrected here and inspected before anything is closed back up. You decide the fixture locations now, not later.
Stage 2: Waterproofing and substrate (days 3 – 5)
Cement board, a bonded waterproofing membrane on the wet walls, and a sloped mud bed or a foam shower pan, depending on which system fits the footprint. This is the stage nobody photographs and everybody regrets skipping. You choose the tile layout and grout lines at the end of this stage, because the substrate dictates where the field tile breaks.
Stage 3: Tile setting (days 5 – 10)
Floor first, then walls, then accents and niches. Large-format porcelain goes down faster than a mosaic sheet but needs a flatter slab, and The Crossings slabs are usually flat enough to skip self-leveling. Grout and caulk cure for a full day before anyone walks on it. Expect a decision on trim: bullnose, Schluter edge, or a mitered return.
Stage 4: Vanity, countertop and fixtures (days 10 – 13)
Cabinet set and leveled, countertop templated if it’s stone, then the sink, faucet, mirror, sconces and exhaust fan. Glass for the shower or tub gets measured after tile is complete, so there’s a deliberate gap between this stage and the enclosure install. This is where the schedule can stretch a week if you’ve chosen a special-order vanity or a fabricated stone top.
Stage 5: Punch and final inspection (days 13 – 15)
We walk it with you, list what needs touch-up, and get the final inspection signed off. Anything that isn’t right gets fixed under our 730-Day Done Right Promise, which runs longer than the standard one-year workmanship warranty most contractors offer.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The options you’ll actually choose between
Most of the price swing in a The Crossings bathroom comes from four decisions. Here’s the honest trade-off on each.
- Vanity: stock, semi-custom, or built-in. A stock cabinet in the $800 – $1,500 range gets you a decent painted or thermofoil finish and installs in a day. Semi-custom runs $1,500 – $3,000 and buys you the exact width and a furniture-grade finish. KraftMaid sits in that middle tier and is what we quote most often for a room this size. A built-in with a stone top pushes past $3,000 but solves an awkward wall.
- Countertop material. Quartz holds up to Florida humidity and doesn’t stain; it’s the default now. Marble looks better in photos and etches from a toothpaste tube. Laminate still has a place in a rental or a flip, and it’s the cheapest way to finish the top.
- Floor tile. Porcelain in a 12×24 or 24×24 format is the sweet spot – fewer grout lines, more slip resistance with a matte finish. Natural stone (travertine, marble) costs 30 – 50% more installed and wants sealing every couple of years in this climate.
- Fixtures. Kohler and similar mid-tier brands get you a reliable cartridge and parts that are still available in ten years. Builder-grade fixtures save a few hundred dollars up front and often need replacing inside five. Mirror and lighting are usually the last decision and the easiest place to overspend.
What Vanities, Tile & Fixtures costs in The Crossings, FL
Our working range for this job in The Crossings is $9,000 – $28,000. The low end is a standard-size guest bath with stock cabinets, porcelain tile and mid-tier fixtures. The high end is a primary bath with a large tiled shower, semi-custom vanity, stone top, and relocated plumbing.
Five things move that number:
- Room size and tile square footage. Every extra 20 square feet of wall tile is material plus a day of labor.
- Relocating plumbing or electrical. Moving a drain in slab-on-grade CBS construction means cutting concrete – that alone can add several thousand dollars.
- Material grade. Going from porcelain to natural stone, or from stock to custom cabinetry, is the single biggest lever.
- Existing condition. Rot behind tile, a failing pan, or old galvanized supply lines change the job once walls are open.
- Permit scope. A like-for-like cosmetic swap needs less paperwork than a layout change with new plumbing rough-in.
A written estimate from us lists each line – demo, rough-in, waterproofing, tile, vanity, fixtures, glass, permit – with the number you see being the number you pay. What’s typically not included: structural repairs found after demo, specialty glass beyond standard, and any fixture you buy yourself. Financing is available at 0% for 18 months, and projects over $10,000 take $1,000 off.
See the difference
Before
After
Before
After
Before
AfterWhat The Crossings homes specifically do to this job
The Crossings is a master-planned Kendall subdivision built mostly between the late 1980s and the 1990s, almost entirely inside ZIP 33186. That means nearly every bathroom we open is original Mediterranean-style CBS construction, and we’re renovating in a community that’s already fully built out, not building new. Permits go through Miami-Dade County and the City of Miami, and every tract here is HOA-governed, so exterior-facing changes – new window in the bath, vent relocation, exterior finishes – need architectural review on top of the county permit. That combination is what makes a The Crossings bathroom different from the unincorporated pockets around it.
Inside, we see the same pattern over and over: original 1990s tile pans that have been weeping for years, cultured marble vanities with failing caulk lines, and single-pane windows fogging from South Florida humidity. Because homes here are hitting the 30-year mark, bathrooms and roofs tend to get tackled in the same few years – homeowners often pair this work with Tile Roofing in The Crossings or Specialty Roofing in The Crossings while the house is already torn up. If you’re planning a wider scope, this work folds naturally into Bathroom Remodeling in The Crossings. We cover the whole of The Crossings and the surrounding Kendall neighborhoods, and our Bathroom Remodeling service handles everything beyond the vanity, tile and fixture package.
Serving The Crossings, FL – Our Local Coverage Area
We serve The Crossings and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked about Vanities, Tile & Fixtures in The Crossings
Two to three weeks of working days for a single bathroom, with the longest stretch being tile cure and the glass measurement gap. Special-order vanities and fabricated stone tops add roughly one to two weeks of lead time before install. Call (844) 761-9356 and we’ll give you a schedule dated from your start, not an average.
Yes for anything involving plumbing or electrical changes, and often for a full tile replacement in a wet area. Miami-Dade County and the City of Miami both require it, and the HOA architectural review runs separately. We pull the permits and pass the inspections – you don’t chase paperwork.
Yes, and that’s the most common job we do in The Crossings. Keeping the drain, supply lines, and layout in place drops the project toward the $9,000 end of the range and takes the shortest schedule. Moving a drain in slab-on-grade construction is what pushes a job up.
The range is $9,000 – $28,000, with most single-bath jobs landing in the middle of that band. The variables are room size, material grade, whether plumbing relocates, and what we find after demo. Call (844) 761-9356 for an exact quote – estimates are free.
Every job is backed by our 730-Day Done Right Promise: if it isn’t right, we make it right, for two full years from completion. That covers workmanship on tile, waterproofing, vanity install and fixture setting. Our technicians have up to 12 years of experience on this kind of work.
Get a free estimate on your The Crossings bathroom
Call (844) 761-9356 and a live person answers, day or night. We’ll set a time to walk your bathroom, measure the tile area, talk through vanity and fixture options, and hand you a written line-item estimate with the permit scope spelled out. No pressure, no vague ranges. Our technicians are background-checked and arrive in uniform, and we’ll tell you straight what your room needs and what it doesn’t.
Written by the team at Groundwork Construction Co.